B R Hodgson scope of works included Metsec SFS, weatherboarding, drylining and plasterboard partitions to 5 no. 6 story blocks of student accommodation.

Laings were facing considerable LED costs if the project was not completed within the time allowance. It was determined that in order to mitigate this a more collaborative approach was required and all subcontractors agreed that, daily programming would be more efficient than projected programming due to the number of trades working in incomplete areas. Meeting on a daily basis gave the completion programme considerable flexibility and almost immediate collaboration between many trades to sustain a correct uniformed flow of works, maximising all trades potential whilst reducing lost time.

← Back to Drywall

B R Hodgson Limited Location: Bath Contractor: Laing O’Rourke Sub-contract Value: £1.4M Sub-contract Period: 52 Weeks