Internal metal stud and external linings to six floors installing approx 40 kilometres of partitions, with a tape and jointed finish. Inclusive of Jumbo stud partitioning to atrium walls with full height feature plasterboard panel. Lead lining to X Ray/scanner rooms, construction of 12 number operating theatres.

Lafarge systems were installed and adapted to suit “value” and specific detailing; in particular “hybrid” partitions were installed and adapted to suit “value” and specific detailing. A full recycling process was initiated for plasterboard waste and metal stud off cuts.

← Back to Drywall

B R Hodgson Limited Location: Oxford Contractor: Carilion Sub-contract Value: £5.3m Sub-contract Period: 110 Weeks