About this Project

Hot rolled steel and metsec to form roof upstands and support structure, 6000m2 Permarock insulated render, 3000m2 Trespa high pressure laminate rainscreen, including weathering details to windows and bespoke aluminium flashings, roof copings and projecting architectural features.

First track programme to two number blocks, called for careful co-ordination and significant labour and on-site supervision levels. BR Hodgson assumed responsibility for, and completed, the detailed design of weathering details throughout the facade following detailed negotiation and value engineering.

B R Hodgson (Holdings) Limited Location: Gillingham Contractor: Berkely Homes Sub-contract Value: £1.7M Sub-contract Period: 25 Weeks